Intervenors: Northern Pass Experts Failed To Identify All Impacted Wetlands

Print More

Garry Rayno photo

Intervenors listen to an environmental panel hired by Northern Pass Transmission project developer Eversource at adjudicative hearings before the start Site Evaluation Committee Tuesday in Concord.

By GARRY RAYNO,
InDepthNH.org

CONCORD — Intervenors in the Northern Pass Transmission project to bring Hydro-Quebec electricity to New England, questioned environmental scientists hired by Eversource about the thoroughness of their review.

Attorneys claimed the scientists failed to identify all the wetlands impacted by the project and questioned if restoration efforts would allow the areas to function as they did before construction of the $1.6 billion, 1,090 megawatt, 192-mile transmission line between the Canadian border and Deerfield.

The adjudicative hearings before the state Site Evaluation Committee are expected to continue into September before regulators determine if the project moves forward.

At Tuesday’s hearing, attorney Amy Manzelli, representing the Society for the Protection of New Hampshire Forests, questioned if the disturbed wetlands would be restored to pre-construction conditions.

Lee Carbonneau, assistant project manager for Normandeau Associates, said where there will be temporary impacts to wetlands, the area would be regraded to match the original condition and seeded to reestablish vegetation native to the wetland to “set the stage of restoration of all functions and values.”

She said a mitigation plan preserving more than 1,600 acres has been developed to address permanently damaged wetlands.

But Manzelli noted there are no site specific plans to address wetlands damaged temporarily by construction, and Carbonneau said that is true but an overall plan has been developed and environmental monitors on the sties would determine exactly what would be needed to restore the areas.

State approvals

The state Department of Environmental Services has approved the project with conditions as has the Department of Transportation.

Manzelli said the Department of Environmental Services will sign off on the restoration of a site if 75 percent of the vegetation has been reestablished in two years

“That 25 percent may never be reestablished,” she noted, and no one would know unless the area is monitored.

But Carbonneau said the company is required to monitor the site the third year after construction and has to provide periodic monitoring reports.

Until DES approves the restoration effort, she said, work would continue to restore the wetlands. “The DES has the final word,” Carbonneau said.

Manzelli noted there are 1,400 restoration sites that will need to be monitored but the precise location, vegetative mapping or photos have not been catalogued.

Carbonneau said enough information has been provided to the DES to adequately restore the wetlands and meet all federal and state standards.

Concord ROW

Another attorney claimed the company failed to delineate thousands of square feet of wetlands along the transmission line’s right-of-way through Concord.

Deputy City Solicitor Danielle Pacik said the city of Concord hired a respected wetlands scientist who found 40 areas Normandeau Associates missed or that will suffer permanent instead of temporary damage due to the construction.

She said Dr. Rick Van De Poll said Normandeau failed to identify 65,947 square feet of wetlands that will be temporarily damaged by construction and 720 square feet that will have permanent impacts.

Pacik said one area is a vernal pool that he recently visited again after he identified the areas in the winter months.

Carbonneau said Van De Poll did his field check in winter and not during the time of year to assess vernal pools. She noted the Army Crops of Engineers checked their work and two scientists can disagree about the exact delineation of an area.

Pacik said if the area is a vernal pool, the sensitive area should be avoided during construction.

There is no reason to revise their maps, Carbonneau said, adding the pool would be dry by summer and no transmission line structures are proposed within the area.

“You have no plans to go back out and check the area?” Pacik asked, and Carbonneau said they did not, but would go into the field to reflag the wetlands boundaries before construction begins.

“There is no question in my mind that we have done an adequate delineation job on this project and that has been affirmed by the Army Corps of Engineers,” Carbonneau said.

Also the Public Utilities Commission approved Northern Pass’s request to cross public waters and public lands to construct the 192-mile hydroelectric transmission line project.

By granting the licenses, the PUC found the crossings will not interfere with the public’s use of the land and waters. 

The adjudicative hearings on the project proposed by Eversource will continue Friday beginning at 9 a.m. with the environmental panel. Site Evaluation Committee members are expected to question the panel Friday

On Thursday, the second of four public comment hearings will be held between 9 a.m and noon with about 40 people expected to address the committee.

Garry Rayno can be reached at garry.rayno@yahoo.com

InDepthNH.org’s previous stories about the SEC hearings.

April 13, Day 1: Eversource NH Chief Quinlan On The Hot Seat At Northern Pass Hearing
April 14, Day 2: Eversource Chief Questioned About ‘Clean’ Energy Claims And Northern Pass Costs
April 17: Day 3: Eversource: Hydro-Quebec Revenues Could Fall Short In Northern Pass’ First Year
April 18: Day 4: Northern Pass’ Potential Health Concerns Debated At Hearing
April 19: Day 5: Concerns Raised About Northern Pass Affecting Health of Sherburne Woods Residents in Deerfield
April 30: Is NH Getting ‘Hoodwinked’ on Health and Safety By Northern Pass?
May 1: Day 6: Testimony: 44 New Access Roads Needed To Build 192-Mile Northern Pass in NH
May 2: Day 7: Northern Pass Expert: 3 Months of Construction Likely In Downtown Plymouth
M
ay 3: Day 8: Project Official: Northern Pass Construction Limited To 7 am to 7 pm, Noise Assessed Daily
May 3: Eversource’s Chief Quinlan Listed as ‘Host’ For Sununu Fundraiser
May 4: Day 9: Grafton County Attorney Grills Northern Pass Experts On Land Buys
May 5: Day 9, story 2: Common Man’s Alex Ray: Northern Pass Disruption in Plymouth Would Be ‘Fatal’ To Business
May 8: Forest Society Calls Northern Pass Inflated Land Buys a ‘Shell Game’
May 25: Hydro-Quebec Explores Opportunities in New England, New York
May 31: InDepthNH.org, NHPR Talk Northern Pass With John Dankosky
May 31: Day 10: ‘Frac-Out’ Water Pollution Possible When Drilling To Bury Northern Pass
J
une 1: Day 11: Applicant: Northern Pass Would Mitigate Impact On Endangered State Butterfly
June 8: Day 12: Counsel for the Public: Northern Pass Financial Expert’s Perspective ‘Unnaturally Optimistic’
June 9: Day 13: Portions of Northern Pass Hearings Held In Closed Session, Again
June 12: Public Statement Hearings On Northern Pass Begin June 15
June 13: Day 14:  Analyst: Customer Using 300 kw Would Save $1.50 a Month With Northern Pass
June 14: Day 15: Regulator: Committee Could Consider Conditioning Approval for Northern Pass
J
une 15: Day 16: Speaking Out For and Against Northern Pass From Connecticut to Concord
J
une 16: Day 17, below:

Forest Society Presses Environmental Benefits of Burying Northern Pass

For more information about InDepthNH.org, which is published online by the New Hampshire Center for Public Interest Journalism, contact Nancy West at nancywestnews@gmail.com or call 603-738-5635

Comments are closed.