One Final Light Is Turned Off for Northern Pass
|
The ownership of land Eversource purchased for the ill-fated Northern Pass Transmission Project has been transferred to the previous owners of the property.
InDepthNH.org (https://indepthnh.org/tag/northern-pass/)
The ownership of land Eversource purchased for the ill-fated Northern Pass Transmission Project has been transferred to the previous owners of the property.
A Maine business court jury paved the way to restart construction on a high-voltage transmission line to carry Hydro-Quebec power to Massachusetts.
As New Hampshire emerges from a long winter of ratepayer discontent, the hunt for blameworthy characters continues. Here are some nominations.
North Country publisher, avid outdoorsman, and well-known writer John D. Harrigan of Colebrook has died at age 75.
However, New England electric ratepayers could collectively reduce their bills by $1.5 billion to $1 billion a year if there were no forward capacity component.
“We have reviewed the record and conclude that the Subcommittee’s findings are supported by competent evidence and are not erroneous as a matter of law” Associate Justice Anna Barbara Hantz Marconi wrote for the court.
Residents and leaders of Newington and Durham mostly oppose the project believing it will affect Little Bay’s water quality and negatively impact historic sites, property values and aesthetics.
Eversource called the court’s acceptance another step forward for the transmission project.
CONCORD — State utility regulators voted 7-0 on Thursday to reject a motion to reconsider their decision turning down the $1.6 billion, 192-mile Northern Pass Transmission project.